CLAVE 1 / 4Germany’s cabinet approved a major rewrite of offshore wind law, extending project lifespans to 35 years and introducing contracts for difference.
CLAVE 2 / 4The August auction for 10.1 GW of North Sea sites collapsed with zero bids, forcing Berlin to scale back 2026 tenders to 2.5–5 GW.
CLAVE 3 / 4Germany has 10.8 GW of installed offshore wind capacity but 17.5 GW of awarded projects remain stalled at final investment decision.
CLAVE 4 / 4The Economy Ministry warned of a "difficult market environment", citing tight supply chains and rising costs for zero-subsidy projects.